fbpx

The Burnaby progress

September was spent working on pouring the foundation footing and walls. This was followed by spraying waterproofing on the foundation. We then installed a drain mat and downspouts as well as connected to the utilities. Since the foundation is complete, we can now focus our efforts on the framing process which will start next week. Once this is complete, we will begin installing all of the windows throughout the frame and roofers will get started.

4546 Coming Soon

4546 Build